TMW completed new upgrade

This TMW team picture is taken in front of a $2,700,000 upgrade to the team’s newly upgraded stretcher leveler multicut blanking line.

It is the world’s first configured line as such and was the culmination of a three month installation and commissioning project.

This upgrade was a critical piece to TMW’s 2024 expansion after adding a 26,400 square feet building expansion to plant 1 and a 36,000 square feet finished goods building to plant 2 to support TMW’s continued growth.